Oregon PGE Sues Backers of Construction Bond for $180M over Shoddy Work
A Portland, Ore.-based electricity provider that fired the contractor building its natural gas plant in Boardman is suing the backers of a bond guaranteeing construction.
The East Oregonian reported Portland General Electric filed the lawsuit March 23 against Liberty Mutual Surety and Zurich North America, the backers of the plant’s $145.6 million performance bond.
Both insurers named in the lawsuit deny liability. The contractor’s parent company says the contract was wrongfully terminated.
PGE’s lawsuit says the company has found potentially dangerous defects since taking over construction of the Carty Generating Station in December.
PGE is seeking $180 million in damages.
- NYC Mayor Eyes City-Run Insurance Program for Affordable Housing
- Marsh Aims to Be ‘AI Winner’ by Focusing on Gains in Growth, Productivity, Efficiency
- Viewpoint: Why Brokers Have Little to Fear and Everything to Gain From AI
- Carnival Cruise Passenger Served 14 Shots Awarded $300,000 After Fall Down Stairs