Idaho City Appeals Ruling over City Hall Construction Flaws
The city of Meridian has appealed a district court ruling that rejected its claims against a contractor hired to build a new $21 million city hall.
In a statement Monday, the city said an appeal had been filed with the Idaho Supreme Court last week.
Fourth District Court Judge Ronald J. Wilper last month rejected the city’s claims that Petra Inc. breached its contractual obligations and should be liable for flaws discovered in the 104,000-square-foot building.
Wilper also determined the city should bear the costs of Petra’s legal fees, estimated $1.8 million.
Meridian sued Petra in April 2009, saying experts had determined the city suffered damages totaling $8.5 million. The deficiencies alleged by the city included misaligned exterior stonework, leaks in the roof, and a faulty heating and air-conditioning system
- Adjusters Launch ‘CarFax for Insurance Claims’ to Vet Carriers’ Damage Estimates
- Experian: AI Agents Could Overtake Human Error as Major Cause of Data Breaches
- Supreme Court Rejects Challenge to $2.46B Boy Scouts Sex Abuse Settlement
- Wildfires, Storms Fuel 2025 Insured Losses of $108 Billion: Munich Re Report